Copper 360 cuts its half-year loss to R96.5m as it bets on Rietberg's higher-grade underground ore

Northern Cape copper producer Copper 360 reported a R96.5m loss for the six months to August, 27% smaller than a year earlier, after cutting costs and debt costs. Revenue fell 20% to R54m after it stopped processing stockpiled material at Rietberg in May. It says first samples from the underground ore body are higher-grade than planned.

Nov 29, 2026 - 20:18
0 0
The flooded open pit of the old Okiep copper mine in Namaqualand with hills behind
The historic Okiep copper mine pit in Namaqualand, Northern Cape, the region where Copper 360 operates (illustrative file photo). Photo: Andrew Hall via Wikimedia Commons, CC BY-SA 3.0

JSE-listed junior miner Copper 360 has reported a smaller loss for the half-year as it cut costs and shifted its focus to the higher-grade underground ore body at its Rietberg mine in the Northern Cape.

The numbers

  • Loss for the six months to 31 August: R96.5m, down 27% year on year
  • Revenue: R54m, down 20%
  • Cost of sales: down 52% to R75.2m; gross loss R21.2m (from R87.8m)
  • Finance costs: down 65% to R21.4m
  • Cash: R11.8m at 31 August, from R84.4m at the end of February
  • Total borrowings: R364.6m, from R304.2m

The shares rose 3.17% to 65c on Friday, Business Day reported.

Why revenue fell

On 8 May the company stopped processing previously mined copper-bearing material at Rietberg after deciding it was no longer financially viable, and placed its MFP2 plant on care and maintenance. The period therefore included only just over two months of production. About 32,058 tonnes of ore were processed at an average feed grade of 0.94% copper, The National reported.

The company cut its workforce from 320 to 240 and stopped non-core in-house crushing, which helped reduce costs.

The Rietberg bet

Copper 360 said it had completed more than 90% of the roughly 520m of planned underground development by the end of August and reached the main ore zone in November. Initial bulk samples suggest a grade of about 1.9% copper, above the 1.33% used in its mine plan. The company stressed that these early results, from the first metres of development, do not change its resource or reserve estimates or its mine plan.

It appointed Cementation Africa in July on a 48-month contract to develop underground access. Plant workers who had been laid off have returned for training ahead of a planned ramp-up in the fourth quarter.

Funding

The group used R83.8m in operating cash in the period. It renewed its R38m overdraft facility in September with the backing of a major shareholder, which has also committed to continued financial support. Taking that support into account, the directors said the group had enough resources to meet its obligations over the next 12 months.

Copper has also featured in other JSE results this month, including Reunert's annual numbers.

Sources

What's Your Reaction?

Like Like 0
Dislike Dislike 0
Love Love 0
Funny Funny 0
Wow Wow 0
Sad Sad 0
Angry Angry 0
Republic Times Newsroom

The Republic Times newsroom: independent, ad-free South African journalism. Story tips and corrections: info@republictimes.co.za.

Comments (0)

User