Google halts work on Belgian AI data centre after authorities call it 'illegal construction'

Google has stopped construction of a large AI data centre in Farciennes, Belgium, after Wallonia's regional authorities said the building went ahead without a valid planning permit. The firm says it has paused works pending further guidance, and a court ruling is expected early next year.

Nov 29, 2026 - 16:13
0 0
A Google data centre building in Eemshaven, the Netherlands
A Google data centre in Eemshaven, the Netherlands, not the Belgian site in the story (file photo). Photo: Ymnes via Wikimedia Commons, CC BY-SA 4.0

Google has stopped work on a large artificial intelligence data centre in southern Belgium after regional authorities said it was being built without a valid permit, the BBC and The Guardian reported.

The company said it had paused the works in Farciennes, near Charleroi in Wallonia, "pending additional guidance". "We have operated in Belgium for over 15 years and remain committed to complying with local laws," Google said.

Why the work was stopped

Google's 2024 permit allowed three smaller, air-cooled data centres. In 2025 it applied to merge two of them into one much larger building and to switch to liquid cooling, drawing 600 cubic metres of water an hour from the nearby River Sambre, The Guardian reported.

The regional administration approved the changes in April, but residents and campaigners appealed, and in August Wallonia's infrastructure minister, François Desquesnes, revoked the amended permit over drought concerns. Work continued anyway, the reports said.

Regional official Raphaël Stokis told broadcaster RTBF that inspectors had found "the building was almost finished, with the structural work completed, even though the permit had been refused", and that about 300 workers had been told to stop. Wallonia government spokesperson Nicolas Yernaux told AFP that a report alleging "a major offence: the illegal construction of a building covering 3 hectares" was being sent to prosecutors.

Greenpeace and the wider backlash

Greenpeace Belgium had published drone footage showing construction continuing. "That Google continues to build without a permit is disrespectful to the environment, local residents, and the law," said Joeri Thijs of Greenpeace Belgium, according to the BBC.

Google has appealed the revocation to Belgium's Council of State, and a ruling is expected on 7 January, The Guardian reported.

The case is part of a growing pushback against the energy- and water-hungry data centres behind the AI boom. In South Africa, the debate is about whether the grid can cope: Eskom says it has about 6GW of spare daytime capacity for data centres, while in the US Donald Trump has threatened to tax companies that build AI data centres abroad.

Sources

What's Your Reaction?

Like Like 0
Dislike Dislike 0
Love Love 0
Funny Funny 0
Wow Wow 0
Sad Sad 0
Angry Angry 0
Republic Times Newsroom

The Republic Times newsroom: independent, ad-free South African journalism. Story tips and corrections: info@republictimes.co.za.

Comments (0)

User