Eskom pitches about 6GW of spare daytime power to AI data centres as load-shedding fades
Eskom chairperson Mteto Nyati says the utility has about 6GW of spare daytime electricity capacity and sees energy-hungry AI data centres as ideal customers. Tech analyst Arthur Goldstuck says this could give South Africa an edge at a time when data centres face grid backlash in the US.
A few years ago South Africans were planning their days around load-shedding schedules. Now Eskom is looking for customers to use its spare power, and it has artificial intelligence in its sights.
What Eskom said
Eskom chairperson Mteto Nyati told the Africa Tech Forum in Cape Town last week that the utility has about 6GW of daytime electricity capacity available, EWN and Wisevoter reported. He said that surplus could give South Africa an advantage in attracting investment in data centres, which need large and reliable supplies of power to run and cool servers.
Nyati also reportedly argued that Eskom's past crisis was caused by poor management rather than a lack of generation capacity.
Why it matters
Arthur Goldstuck, chief executive of World Wide Worx, told CapeTalk that this is a contrast with the United States, where data centres have faced a backlash because of the strain they put on already stretched grids. In South Africa, he said, spare capacity could instead support expansion, EWN reported.
Goldstuck also pointed to data centre operators investing in their own renewable energy, citing Teraco's planned 120MW solar plant in the Free State. If that trend continues, he said, AI infrastructure investment could add to the country's electricity supply rather than only drawing on it.
The fine print
The figure is daytime capacity, when solar output is highest and demand is lower; evening peaks remain tighter. Eskom has not published a tariff offer or a list of data centre deals linked to the pitch. Earlier this month Eskom marked 550 days without load-shedding, and other heavy users have argued that cheaper power for industry is overdue, with smelter Transalloys blaming a delayed tariff decision for planned job cuts.
Related: Eskom: 550 days without load-shedding · Trump's data centre tax threat and South Africa · Transalloys and the Eskom tariff delay