Eskom study puts new nuclear build at R471bn to R1.66 trillion, private ownership on the table
Eskom's feasibility study for 5,200MW of new nuclear power puts the cost at between R471 billion and R1.66 trillion, the Sunday Times reports. The figures are benchmarks, not a budget, and private-sector participation is one of the funding models being considered.
South Africa's planned new nuclear power stations could cost anywhere from R471 billion to R1.66 trillion, according to an Eskom feasibility study reported by the Sunday Times.
The study was submitted to Electricity and Energy Minister Kgosientsho Ramokgopa earlier this month. It covers a 5,200MW programme: 4,800MW of large pressurised water reactors and 400MW of small modular reactors.
Not a budget
Eskom stresses that the figures are benchmark ranges, not an approved budget. Reactor design, vendors, the construction schedule, financing terms and exchange rates have not been decided, the newspaper reports.
The study lists affordability and financing as a weakness. It warns of high upfront costs, a long period before the plants earn revenue, and exposure to currency swings, interest rates and delays, which could affect Eskom's balance sheet, electricity tariffs and the need for state support.
Who would own it?
The ownership structure is still open. Two broad models are being looked at, according to the study: a traditional engineering, procurement and construction contract funded with debt, or a private-sector participation model that combines equity from public, private, vendor or development finance sources.
Why Eskom says it matters
Eskom argues that nuclear power should not be judged on upfront cost alone, pointing to its long life of about 60 years and the jobs and economic activity linked to Koeberg. It warns that a five-year delay could leave the country short of dispatchable power from about 2036 as coal stations retire, and increase reliance on more expensive gas.
The new build is part of the 2025 Integrated Resource Plan, which targets 5,200MW of new nuclear capacity by 2039. On Friday Ramokgopa gazetted his intention to make a section 34 determination to start procurement, after consulting the finance minister.
The Department of Electricity and Energy published the feasibility report in the Government Gazette (No. 55810, Notice 8226) on 27 November 2026. The report calls the cost figures Class 4 estimates, with an expected accuracy range of about minus 30% to plus 50%, and says it does not select a reactor design, vendor or site.