Ramokgopa gazettes plan for 5,200 MW of new nuclear power, with cost estimates of up to R1.4 trillion for a large reactor

Electricity and Energy Minister Kgosientsho Ramokgopa has published notice of his intention to make a Section 34 determination for 5,200 MW of new nuclear generation, together with a feasibility report that puts early cost estimates for a large reactor at R390 billion to R1.4 trillion.

Nov 28, 2026 - 06:20
Updated: 40 minutes ago
0 0
Koeberg nuclear power station buildings on the coast north of Cape Town under a partly cloudy sky
Koeberg nuclear power station near Cape Town, South Africa's only nuclear plant (file photo). Photo: Paul Scott via Wikimedia Commons, CC BY-SA 2.0

Electricity and Energy Minister Kgosientsho Ramokgopa has formally started the process to procure 5,200 MW of new nuclear generation capacity. Green Building Africa reports that he published Government Gazette Notice No. 8226 on 27 November, stating his intention to make a determination under Section 34 of the Electricity Regulation Act. A Section 34 determination is the legal step that allows new generation capacity to be procured. The 5,200 MW figure comes from the 2025 Integrated Resource Plan (IRP).

Earlier this month, Ramokgopa told a nuclear conference in Pretoria that a "case for nuclear" document would be released for 60 days of public comment at the end of November, Engineering News and TechCentral reported. He said he aimed to finalise the determination between April and June 2027, after getting concurrence from the energy regulator NERSA and National Treasury.

What the notice does, and does not do

Green Building Africa says a determination would allow market engagement and preparation of a business case to begin. It would not approve funding, a site, a vendor or construction. The feasibility report published with the notice says no government guarantee, fiscal contribution or revenue arrangement has been approved.

Early cost estimates

The report puts the overnight capital cost of one large pressurised water reactor at between R390 billion and R1.402 trillion, and between R471 billion and R1.667 trillion in nominal terms. It gives an indicative electricity cost of R2,423 to R5,065 per megawatt-hour. The report describes these as early-stage (Class 4) estimates, not vendor prices or approved budgets, with an accuracy range of minus 30% to plus 50%.

Sites and technology

The capacity is expected to come from large reactors and small modular reactors (SMRs) at coastal sites, and possibly SMRs at old coal-plant sites. The smallest programme considered viable is two large units at one site. Early site work focuses on Duynefontyn, next to Koeberg in the Western Cape, and Thyspunt in the Eastern Cape, with Bantamsklip as an alternative. The environmental authorisation for Duynefontyn is under judicial review, Green Building Africa notes.

The report lists affordability, currency swings, cost and schedule overruns, litigation and public opposition among the main risks. It recommends that a final investment decision be taken only after market responses, financing and regulatory approvals have been independently checked. Engineering News notes that three earlier attempts to procure new nuclear since 2008 failed.

The notice comes as Eskom reports its best plant availability in years. Related: Eskom marks 550 days without load-shedding and Eskom's spare daytime capacity.

Sources

What's Your Reaction?

Like Like 0
Dislike Dislike 0
Love Love 0
Funny Funny 0
Wow Wow 0
Sad Sad 0
Angry Angry 0
Republic Times Newsroom

The Republic Times newsroom: independent, ad-free South African journalism. Story tips and corrections: info@republictimes.co.za.

Comments (0)

User