Limpopo’s Morebeng–Sekgosese road, delayed for nine years and once shown off to Ramaphosa, is finally due to open by January

A R400m road project linking villages in Limpopo’s Mopani and Capricorn districts, started in 2017 and abandoned by contractors, is due to be finished by January 2027, officials told The Citizen. Premier Phophi Ramathuba ordered a forensic probe after a Roads Agency Limpopo manager paid the failed contractor a R20m retention fee.

Nov 22, 2026 - 08:17
0 0
A tarred road in Limpopo at dusk with cars heading towards hills
A provincial road in Limpopo (illustrative file photo; not the Morebeng–Sekgosese route). Photo: JMK via Wikimedia Commons, CC BY-SA 4.0

A Limpopo road project that has missed deadlines for nine years, and that President Cyril Ramaphosa inspected in 2022, is now expected to open to traffic by early next year, according to the Roads Agency Limpopo (RAL) and the provincial public works department.

Nine years of delays

The 33km, R400 million project, which runs from road D15 at Morebeng to D3232 in the Sekgosese area of the Greater Letaba municipality, was commissioned in 2017 under then-premier Stanley Mathabatha, The Citizen reported. Contractors abandoned it a few years later. When finished, the gravel-to-tar route is meant to connect eight villages across the Mopani and Capricorn districts.

Ramaphosa visited the stalled project in February 2022. The Citizen reported that officials allegedly assured him then that it would be finished before the 2024 elections. It was not.

Premier Phophi Ramathuba later ordered that the road be completed and asked the provincial public works department to carry out a forensic investigation. Among other things, it is looking into allegations that a senior RAL manager irregularly paid the failed contractor. RAL has confirmed that the manager paid the contractor a R20 million retention fee, according to The Citizen. The findings of the investigation have not been made public.

Where the work stands

A new contractor, Mathothoka Trading CC, was appointed on 18 August 2025 to finish the remaining work at a cost of about R107.5 million. The remaining scope was 3.5km of road D3150 and two bridges.

RAL chief executive Makhitha Chesane told The Citizen that the 3.5km of road had been tarred as promised, and that the road and bridges should be ready between December and January. Public works spokesperson Tendani Munyai said structural work on the first bridge was complete, but that floods between December 2025 and March 2026 meant the second bridge needed an extra span. Its completion is now targeted for 30 January 2027. The contractor said the project had created 37 local jobs.

‘Let them finish first’

Residents told the newspaper the road would cut a two-hour trip to Soekmekaar to about 30 minutes. Others were more cautious, saying they would believe it when the road was fully open.

Related: Limpopo’s women mayors: 13 of 22, but parity without power? | Polokwane council sitting collapses

Sources

What's Your Reaction?

Like Like 0
Dislike Dislike 0
Love Love 0
Funny Funny 0
Wow Wow 0
Sad Sad 0
Angry Angry 0
Republic Times Newsroom

The Republic Times newsroom: independent, ad-free South African journalism. Story tips and corrections: info@republictimes.co.za.

Comments (0)

User