Opinion: Finishing the Morebeng road is good news, but Limpopo should publish what went wrong

Republic Times opinion: residents of Sekgosese deserve their road, and the provincial government deserves credit for pushing it to completion. But a project that missed deadlines for nine years, saw R20m paid to a contractor who left, and was shown to the President as almost done, needs a public explanation. Publish the forensic findings.

Nov 22, 2026 - 08:17
0 0
Plantations and hills along the R71 near Haenertsburg in Limpopo
Hills and plantations along the R71 near Haenertsburg, Limpopo (illustrative file photo). Photo: JMK via Wikimedia Commons, CC BY-SA 4.0

This is an opinion and analysis piece reflecting the view of Republic Times. It is based on the published facts linked below.

For residents of Sekgosese and the villages along the Morebeng road in Limpopo, news that their road should open by January is the best kind of news. One resident told The Citizen it would cut a two-hour trip to about 30 minutes. That is real time and money for people who have waited since 2017. Our news report has the details.

Credit is due where it is earned. Premier Phophi Ramathuba appointed a new contractor in August 2025, ordered a forensic investigation, and officials have now given a clear date for the last bridge: 30 January 2027. Floods earlier this year explain some of the latest delay, and that is a reasonable explanation.

But the story is bigger than a bridge

The facts on record are uncomfortable. A R400 million project was commissioned in 2017 and abandoned by contractors. The Roads Agency Limpopo has confirmed that a senior manager paid the failed contractor a R20 million retention fee, money that is normally held back precisely to make sure a job is finished properly. In 2022 the President was taken to the site and, according to The Citizen’s reporting, assured it would be done before the 2024 elections. Finishing what remained has since cost another R107 million.

None of this proves wrongdoing by any individual, and everyone named deserves a fair hearing. That is exactly why the forensic investigation matters. Its findings should be made public, with the names of officials and companies where the evidence supports it, and with any recovery steps or disciplinary action spelled out.

Three simple asks

First, publish the forensic report, or at least a full summary, once it is complete. Second, say whether the R20 million retention payment can be recovered. Third, give residents of every stalled provincial road project a simple public dashboard: budget, contractor, money spent, percentage complete and the next deadline.

South Africa has too many projects that are always “nearly complete” in election years. The way to end that is not more ribbon-cutting, but making the paper trail visible. Limpopo has a chance to show how it is done.

Related: Opinion: every rand for youth jobs should be traceable

Sources

What's Your Reaction?

Like Like 0
Dislike Dislike 0
Love Love 0
Funny Funny 0
Wow Wow 0
Sad Sad 0
Angry Angry 0
Republic Times Newsroom

The Republic Times newsroom: independent, ad-free South African journalism. Story tips and corrections: info@republictimes.co.za.

Comments (0)

User