Opinion: When medicine waits at sea, Durban’s port crisis needs a public scoreboard, not just another plan
Republic Times opinion: Transnet and Durban Gateway Terminal have admitted to years of underinvestment and promised new equipment until 2028. With medicines stuck on ships and festive stock delayed, the operators should publish weekly figures on waiting ships, waiting times and working equipment so the public can judge the recovery.
This is an opinion piece reflecting the view of Republic Times. It is based on facts reported by the sources listed below.
The Department of Health had to send Transnet a list of 16 ships carrying medicines that needed to be cleared urgently from the Port of Durban. By Friday, six had been cleared. Three were due to berth in the coming days. Seven were still at sea.
That list tells you most of what you need to know about the state of South Africa’s busiest container port.
Credit where it is due
The response this week has been more honest than usual. Durban Gateway Terminal (DGT) said plainly that poor and unsafe equipment, caused by years of underinvestment and inadequate maintenance, lay at the heart of the problem. It acknowledged “continued service shortcomings”. Transnet has opened extra berths, brought refurbished cranes back into service, put on trains to Gauteng and is prioritising medicines and car parts. Admitting the problem is the first step to fixing it.
It is also fair to note that the causes go back years and cannot all be blamed on this year’s reforms or on the private partner that now owns 49% of the terminal. Both sides of the privatisation argument have their talking points. Neither will clear a single container.
Why a plan is not enough
The recovery depends on equipment arriving in stages until 2028. Businesses report waiting up to 20 days for cargo, and News24 reports that the backlog has already delayed festive stock for Mr Price. Unisa’s Dr Simphiwe Madikizela warns that the measures may bring temporary relief without fixing the structural weaknesses.
South Africans have heard many port recovery plans before. What has usually been missing is a way for the public to see, week by week, whether the plan is working.
Publish the numbers
We think Transnet and DGT should publish a simple weekly scoreboard. It should show:
- how many ships are waiting at anchorage, and the average waiting time;
- how long import containers spend in the terminal (DGT says about three days now);
- how many cranes, straddle carriers and other machines are actually working;
- whether each promised delivery of new equipment has arrived on time;
- how many of the vessels carrying medicines have been cleared.
None of this would cost much. Much of it is presumably already tracked internally. Making it public would let shippers plan, and would let Parliament, the shareholder ministry and the public hold the operators to their own promises.
When a hospital pharmacy runs short because a container is stuck on a ship, the port is not just a business problem. It deserves the openness we would expect of any public emergency.
Related: Medicines stuck on 16 ships: Transnet clears six; Transnet rushes extra berths and cranes to Durban
Sources
- The National — Durban Gateway Terminal rolls out equipment plan as vessel backlog persists
- SAnews — Cargo with critical pharmaceutical products prioritised at the Port of Durban
- SAnews — Efforts to reduce backlogs at the Port of Durban
- Sunday World — Transnet clears six vessels as DGT races to ease congestion
- News24 — Durban crisis delays Mr Price’s festive season stock